Yesterday, the Laskin Energy Project team had a design review with our client. The client contacts present were Kristopher Spenningsby and Eric Kunnari. In the design review, the team presented the progress made on the project, the next steps, and then worked through a couple hang ups. After showing the work accomplished on the user interface, efficiency calculation and corresponding instrumentation tags, components where discussed and a few changes made. Overall, the client was satisfied with the work accomplished, provided feedback on a couple components and stated the direction that they would like to see taken. The project is on track to finish November 24, 2010 one week ahead of the due date.